Attachment F. BUILDING-BY-BUILDING RE-OCCUPANCY
NEW YORK CITY COLLEGE OF TECHNOLOGY
BUILDING-BY-BUILDING RE-OCCUPANCY PLAN: Phase 1
CAMPUS HOURS OF OPERATION: Campus is closed, except for scheduled on-campus labs and by appointment. All buildings are open for essential personnel.
BUILDING | COMMENTS |
---|---|
Namm | Open for construction |
Library Building | Closed |
General Building | Closed |
Pearl Building | 2nd floor open for construction |
New Academic Building | Lab classes on 4th, 5th, 6th, 7th, and 8th floors |
Voorhees | Closed |
Environmental Technology | Closed |
Midway | Closed |
Howard | 4th floor closed 11th floor open for essential only |
BUILDING-BY-BUILDING RE-OCCUPANCY PLAN: Phase 2
CAMPUS HOURS OF OPERATION: Campus is closed, except for scheduled on-campus labs and by appointment. All buildings are open for essential personnel.
BUILDING | COMMENTS |
---|---|
Namm | Open for construction |
Library Building | Closed |
General Building | Day Care Center Open |
Pearl Building | 2nd floor open for construction |
New Academic Building | Lab classes on 4th, 5th, 6th, 7th, and 8th floors |
Voorhees | Selected Engineering, Architecture and Entertainment Technology Labs open |
Environmental Technology | Closed |
Midway | Closed |
Howard | 4th floor closed 11th floor open for essential HR and Business Office |
BUILDING-BY-BUILDING RE-OCCUPANCY PLAN: Phase 3
CAMPUS HOURS OF OPERATION: Campus is closed, except for scheduled on-campus labs and by appointment. All buildings are open for essential personnel. Faculty may work on campus.
BUILDING | COMMENTS |
---|---|
Namm | Open for construction. Faculty may hold classes and labs. |
Library Building | Partial opening |
General Building | Day Care center and Computer Lab open. |
Pearl Building | 2nd floor open for construction. Faculty Offices and labs open. |
New Academic Building | Lab classes on 4th, 5th, 6th, 7th, and 8th floors. |
Voorhees | Open for in Person classes and labs. |
Environmental Technology | Open for classes. |
Midway | Under Construction. |
Howard | 4th floor open for Continuing Education 11th floor open for staff |
BUILDING-BY-BUILDING RE-OCCUPANCY PLAN: Phase 4
CAMPUS HOURS OF OPERATION: Campus is closed, except for scheduled on-campus labs and by appointment. All buildings are open for students, faculty and staff.
BUILDING | COMMENTS |
---|---|
Namm | Open for construction and students, faculty and staff. Student Services open |
Library Building | Open |
General Building | Open |
Pearl Building | 2nd floor open for construction. Open for students, faculty and staff. |
New Academic Building | Labs and classrooms open. |
Voorhees | Labs and classrooms open. |
Environmental Technology | Labs, classrooms and offices open. |
Midway | 4th floor closed. |
Howard | 4th closed 11th floor open for essential personnel only |
BUILDING-BY-BUILDING RE-OCCUPANCY PLAN: Phase 5
CAMPUS HOURS OF OPERATION: All buildings are open for students, faculty and staff. DURING NORMAL BUSINESS HOURS.